Skip to content
03Handover & Transition

Under FIDIC, taking over comes before acceptance

Under FIDIC 2017, taking over and contractual acceptance of the works are separate. At taking over the owner takes possession and may begin operating; Sub-Clause 11.9 makes the Performance Certificate the document that constitutes acceptance, and it follows a Defects Notification Period of one year unless the Contract Data states otherwise. A general law-firm summary lists what can change at practical completion or taking over: the contractor's insurance of the works ends, the risk of loss transfers, exposure to delay damages stops, and, where the contract provides for it, retention and the performance bond can begin to release. Where they do, much of the hold on the contractor loosens just as the owner's exposure begins.

Updated 2 October 20269 min read

Handover is discussed as a moment. It is not one. It is a boundary between two states, and the two states are less different than people assume in one respect and far more different in another.

Under FIDIC 2017 the two events are separate. At taking over the owner takes possession of the works and may begin operating them. Contractual acceptance of the works comes later: Sub-Clause 11.9 makes the Performance Certificate the document that constitutes it, and the certificate follows the Defects Notification Period, which is one year where the Contract Data states no different period.

Almost everything commercially interesting happens in between.

What actually changes on the day

Set out plainly, the list is longer and more one-sided than most owners expect. Fenwick Elliott's summary of contractual liabilities after completion, a general account of practical completion and taking over rather than a reading of any one standard form, lists these as the significance of that day:

  • The employer takes possession of the site and the works.
  • The contractor's insurance of the works ends, and the risk of loss or damage to the works transfers to the employer.
  • The contractor's exposure to delay damages ends.
  • The contractor's obligation to undertake variations ends.
  • The first instalment of retention is released.
  • The performance bond can release.
  • The defects rectification period is triggered.
  • The final account can commence.

Which of these applies, and when, is set by the contract in use. Under any given form, retention and the performance security are released on that form's own terms. Read that as a sequence of transfers rather than a checklist. On one day, the party that has been carrying the works stops carrying them, the financial instruments holding it to the contract may begin to unwind where the contract provides for it, and the party taking possession has, at that moment, the least operating experience of the asset it will ever have.

The third clock on the same day: when finance moves the balance, and on what evidence

, read: The evidence finance needs is in a file finance never sees
Projects Advisors. Reuse: https://projects-advisors.com/licenceUnder FIDIC 2017, the window between taking over and acceptanceA timeline of four overlapping periods under FIDIC 2017. The contractor carries the works until taking over. From taking over the owner has possession and may operate. The works are accepted only from the performance certificate, which Sub-Clause 11.9 makes the document of acceptance, after a defects notification period of one year unless the Contract Data states otherwise. In Saudi Arabia, decennial liability runs for ten years from the occupancy certificate, a third date. The horizontal scale is compressed after the performance certificate.Taking overPerformance certificateTen yearsContractor carries the worksOwner has possessionWorks accepted, Sub-Clause 11.9Saudi decennial liabilityDefects notification period: one year unless the Contract Data differsScale compressedInsurance and delay damages end at the left edge of the window in whichthe owner holds works not yet accepted under FIDIC 2017.
FIG. 01Under FIDIC 2017, taking over and acceptance are separate events. At taking over the owner takes possession and may begin operating; Sub-Clause 11.9 makes the Performance Certificate, issued after a Defects Notification Period of one year unless the Contract Data states otherwise, the document that constitutes acceptance. In Saudi Arabia, decennial liability runs from a third date, the occupancy certificate, for ten years. Whether the security and the retention holding the contractor to the contract reduce at the start of the window or stay to its end is set by the contract in use.

Complete does not mean free of defects

The other assumption worth dismantling is that completion means the works are finished.

English case law is direct about this, and the reasoning is portable even where the law is not. In Mears Ltd v Costplan Services (South East) Ltd, the Court of Appeal observed that practical completion is easier to recognise than to define, and settled several points that surprise people.

The existence of latent defects cannot prevent practical completion, which follows from the definition of latent: nobody knows about them yet. Patent defects can be present provided they are trifling, and what counts as trifling is a matter of fact and degree, measured against the purpose of letting the employer take possession and use the works as intended. And the fact that a defect is irremediable does not necessarily mean the works are not practically complete.

FIDIC's 2017 conditions, as the same Fenwick Elliott summary sets them out, take a similar position from the other direction. Sub-Clause 10.1 permits minor outstanding work and defects that do not substantially affect the safe use of the works for their intended purpose, and it contains a deemed taking over provision.

So the asset the owner takes possession of is, by design, permitted to have things wrong with it.

The rectification that is not free

There is a widely held belief that the defects period means the contractor will come back and fix whatever appears. It is half right, and the wrong half is expensive.

On the same summary, under FIDIC 2017 the employer is entitled to notify defects or damage during the defects notification period, and the contractor is obliged to rectify all of it, including defects or damage it did not cause. But where the defect is not the contractor's responsibility, the work is treated as a variation and attracts additional payment under Sub-Clause 11.2, as does additional testing under Sub-Clause 11.6.

Which means the defects period is not a warranty. It is a mechanism guaranteeing that somebody competent will attend, with the question of who pays settled afterwards, on evidence.

That evidence is generated by the owner, during the window, while the owner is operating. Operating records, maintenance logs, alarm histories, commissioning data and the condition of the asset at takeover are the material on which responsibility later turns. They are usually being created by a team that has just arrived and has not been told they are evidence.

Whether that team was ever ready to receive the asset

, read: Completion describes the asset. Readiness describes the owner.

A third clock, and in this region it runs longest

Everything above is contractual and can be negotiated. The regime that cannot be negotiated away is statutory, and in the Gulf it is unusually strong.

In Saudi Arabia the civil code is silent on decennial liability, but the liability exists elsewhere. On Pinsent Masons' reading, Article 29 of the Implementing Regulations of the Saudi Building Code Application Law provides that the supervising designer and the contractor are jointly responsible for compensating the owner for ten years, running from the date of issuance of the occupancy certificate, for total or partial demolition of what they built and for every hidden defect that threatens the durability and safety of the building.

Note the Saudi start date. Not taking over, and not the performance certificate. A third event, on a third clock.

In the UAE the equivalent has long sat in the civil code itself, holding contractors and consultants liable for ten years where a structure suffers total or partial collapse or a defect threatens its stability or safety. The regime is strict: no proof of fault is required.

That framework was recodified this year. Federal Decree-Law No. 25 of 2025, the new UAE Civil Code, took effect on 1 June 2026 and largely preserves decennial liability while adding an express provision that it does not apply to a contractor's right of recourse against subcontractors.

The consequence of that addition is worth stating carefully, because it creates an asymmetry rather than removing one. A contractor or designer carries ten years of strict liability upward to the owner, but any recovery downward against a subcontractor requires proof of fault or breach and causation. Kennedys notes that the limitation period for claims under commercial construction contracts is five years, so a recovery action against a subcontractor may be time-barred well before a decennial claim is brought against the contractor.

For an owner the practical reading is not about who recovers from whom. It is that the parties carrying ten years of exposure may have five years of protection, and a party in that position behaves differently when a defect appears in year seven.

What to examine

  • Establish the three dates and write them down: taking over, expected performance certificate and, on a Saudi project, the occupancy certificate that starts the statutory clock. They are frequently held by three different teams.
  • Find the event on which the contract passes care of the works and the risk of loss or damage, which may be taking over, and check the insurance position on the day after it. If the contractor's cover of the works ends then, the owner's operational policy is not always in force on the same date.
  • Ask who is briefed to keep operating records as evidence during the defects period, and whether anybody has told the operations team that is part of the job.
  • Confirm the retention and bond release schedule against the defects period, rather than against completion. Instruments released early are not recoverable by argument later.
  • For statutory liability, confirm which entities carry it and whether they will still exist in year eight. A ten-year liability against a project-specific company is a liability against nothing.

Nothing here is about pursuing anybody. It is about knowing which state the asset is in, which is a question the certificate on the wall does not answer.


Sources. Jatinder Garcha and Edward Colclough of Fenwick Elliott, Contractual liabilities post completion, 28 January 2021, for what changes at practical completion or taking over, for its summary of FIDIC 2017 Sub-Clause 10.1 on taking over and Sub-Clauses 11.2 and 11.6 on defects notification and rectification not caused by the contractor, on which the statements here about those three Sub-Clauses rest, and for the summary of Mears Ltd v Costplan Services (South East) Ltd [2019] EWCA Civ 502. Cremona Cotovelea, Nina Tsaturova and Jeremy Glover, Differences between the Civil and Common Law, Part 2: Delay Damages and Taking-Over, a conference presentation published by FIDIC, slide 9, which quotes Red Book Sub-Clause 11.9 making the Performance Certificate the only document deemed to constitute acceptance of the Works. Le The Hung, Tran Pham Hoang Tung and Nguyen Huy Nhat Duy of CNC Vietnam Law Firm, the Vietnam report in FIDIC, Construction Law International, International Bar Association, 17 October 2023, for the works under the FIDIC Conditions being accepted only when the Performance Certificate is issued, after the Defects Notification Period, as distinct from taking over. Victoria Tyson of Howard Kennedy, FIDIC 2017: Clause 11, Defects After Taking Over, page 3, for the Defects Notification Period being the period stated in the Contract Data, or one year where none is stated. Pinsent Masons, Saudi Arabia's Civil Code: need to know for construction projects, for the position on decennial liability in Saudi Arabia and the quoted text of Article 29 of the Implementing Regulations of the Saudi Building Code Application Law. Kennedys, UAE Civil Code 2026: decennial liability and subcontractors, for Federal Decree-Law No. 25 of 2025 taking effect on 1 June 2026, the new provision on recourse against subcontractors, and the five-year limitation period for commercial construction contract claims. Law firm commentary is attributed rather than treated as primary, and the statutory position in any jurisdiction should be confirmed locally.

Read the sources

  • Cotovelea, Tsaturova and Glover, Differences between the Civil and Common Law, Part 2: Delay Damages and Taking-Overslides 2 and 9, conference presentation; read 2026-09-25.Free, a conference presentation published by FIDIC. Slide 2 quotes Sub-Clause 10.1 on taking over, and slide 9 quotes Red Book Sub-Clause 11.9: only the Performance Certificate is deemed to constitute acceptance of the Works.
  • International Bar Association, FIDIC, Construction Law International, October 2023Construction Law International, 17 October 2023; read 2026-09-25.Free. Country reports on the FIDIC forms. The Vietnam report, by CNC Vietnam Law Firm, distinguishes taking over from acceptance: under the FIDIC Conditions the works are accepted only when the Performance Certificate is issued under Sub-Clause 11.9, after the Defects Notification Period, whereas Vietnamese law treats taking over as acceptance.
  • Tyson, FIDIC 2017: Clause 11, Defects After Taking Over, Howard KennedyFIDIC 2017 second edition, clause commentary; read 2026-09-25.Free. A clause-by-clause commentary that quotes the periods, including the two-year cap on extending the DNP. It also lists a Notice of No-objection to the as-built records as a new precondition to the Performance Certificate. That is the position in the 2017 Yellow and Silver Books, whose Sub-Clause 11.9 adds it. The 2017 Red Book differs: its Sub-Clause 10.1 makes the as-built and O&M No-objection conditions, where they apply, conditions of taking over, and its Sub-Clause 11.9 does not add that Notice.
ShareLinkedInX

Related reading

A delivered file is not an accepted record

A handover contract can test that the information arrived and that the Engineer had no objection to it. That proves receipt. It does not prove that the data passed a schema, that its identifiers reconcile with the finance and maintenance records, or that the receiving system can run a transaction on it. Those are three further tests, and where a contract's information conditions end at delivery and absence of objection, each can fail while those information obligations are performed in full.

Read

The project crosswalk reaches capitalisation. What survives it?

NASA requires a project work breakdown structure to correlate exactly through seven levels to the financial accounting structure, and EXPRO's cost and commitment procedure reconciles the project cost report to the corporate general ledger on a named form with a named owner. Both requirements are scoped to the project. The Saudi Ministry of Finance's asset manual then has finance allocate the project's cost to assets and components at capitalisation. None of the public documents reviewed here says the project's identifiers stay on the asset record after that.

Read