Skip to content
Projects Advisors

Glossary · Handover & Transition

Defects Notification Period

The period after taking over during which the employer may notify defects in the works and the contractor is obliged to return and rectify them, called the Defects Liability Period in older forms.

FIDIC’s 1999 and 2017 editions call it the Defects Notification Period, where many other forms say Defects Liability Period. The FIDIC name fits what the period limits: when defects may be notified, not how long the contractor is liable. As Tyson’s commentary on the 2017 edition describes it, the period is the one stated in the Contract Data, or 1 year where none is stated, and under Sub-Clause 11.3 an extension may not run more than 2 years beyond the expiry of the stated period.

Its scope is broader than a warranty and narrower than assumed, in the same movement. Published commentary on the 2017 conditions describes the contractor as obliged to rectify everything notified, including defects and damage it did not cause; where the cause is not the contractor’s responsibility, Sub-Clause 11.2 treats the work as if the Engineer had instructed it, so it is a variation and is paid for. The cost runs the other way for defects caused by improper operation or maintenance that trace back to the contractor’s as-built records, manuals or training: in the 2017 Red Book, Sub-Clause 11.2 leaves those with the contractor. The period guarantees attendance by the party that built the works. It does not guarantee that the attendance is free.

At its end comes the Performance Certificate. Tyson’s commentary records that Sub-Clause 11.9 issues it when the contractor has fulfilled its obligations under the contract. In the 2017 Red Book its only information condition is that all Contractor’s Documents have been supplied, and the Engineer’s Notice of No-objection to the as-built records and the manuals is a condition of taking over, under Sub-Clause 10.1; the Yellow and Silver Books add that Notice to Sub-Clause 11.9. A conference presentation published by FIDIC quotes Sub-Clause 11.9 as making the Performance Certificate the only document deemed to constitute acceptance of the Works. The period is therefore better understood as the final phase of the contract than as an after-sales arrangement bolted onto a finished one.

Sources

Victoria Tyson, FIDIC 2017: Clause 11, Defects After Taking Over, Howard Kennedy, on Sub-Clauses 11.2, 11.3 and 11.9 and the 1-year default in the Contract Data definition. Jatinder Garcha and Edward Colclough, Fenwick Elliott, Contractual liabilities post completion, 28 January 2021, on rectification of defects the contractor did not cause, and on a defects period not being an exclusive remedy unless the contract clearly says so. Cotovelea, Tsaturova and Glover, Differences between the Civil and Common Law, Part 2: Delay Damages and Taking-Over, a presentation published by FIDIC, slide 9, for the quoted text of Sub-Clause 11.9 on acceptance. Victoria Tyson, FIDIC 2017: Clause 10, Employer’s Taking Over, Howard Kennedy, on the Notices of No-objection under Sub-Clause 10.1. FIDIC, Conditions of Contract for Construction (the Red Book), second edition 2017, Sub-Clauses 11.2 and 11.9 for their conditions. Institute of Construction Claims Practitioners, Notices under FIDIC Red, Yellow and Silver 2017 Editions, Part 3, October 2022, on Sub-Clause 11.9 in the three books. Pinsent Masons, Saudi Arabia’s Civil Code: need to know for construction projects, on Article 29 of the Implementing Regulations of the Saudi Building Code Application Law, for decennial liability in Saudi Arabia. Kennedys, UAE Civil Code 2026: decennial liability and subcontractors, for decennial liability in the UAE.

Cite this page

Projects Advisors, “Defects Notification Period,” revised 2026-11-02, https://projects-advisors.com/reference/defects-notification-period