Skip to content
Projects Advisors

Insights · Filed by stage

Writing on what happens between building something and owning it.

Structural rather than anecdotal. Each piece belongs to one stage of the lifecycle and examines one recurring failure, with the reasoning shown rather than asserted.

Stage 01

Inception & Development

The decisions taken before anything is built, and the operating consequences they quietly fix in place.

The stage
  1. 01.0101 Inception & Development

    Operations is told to take part in the business case. Nobody asks it to sign.

    Business case method already asks for the operating cost and for affordability across the asset's life, and EXPRO's business case procedures, built on HM Treasury's guide, ask for both. What the documents reviewed here do not ask for is a record that the unit which will run the asset has accepted the operating estimate as a claim on its future budget. The capital sum has an approver. The running cost has a description and a statement of support.

    16 min read · Read
  2. 01.0201 Inception & Development

    A lifecycle ratio nobody can check, and a conclusion that does not need it

    Saudi Arabia's national manual for asset and facilities management opens by stating that construction is only 20% to 30% of an asset's lifecycle cost. The recommendation it draws from that is correct. The number itself belongs to a family of ratios with a documented provenance problem, and the manual's own argument would be stronger without it.

    7 min read · Read
  3. 01.0301 Inception & Development

    Doing the project right, and doing the right project

    Almost every instrument the industry owns answers the first question. Estimating, cost control, scheduling, gateways, technical assurance, internal audit, all of them examine execution. Whether this should have been the project at all is settled once, early, by fewer people, and becomes progressively harder to ask.

    7 min read · Read
  4. 01.0401 Inception & Development

    Every appraisal can be right and the portfolio still wrong

    The Green Book states plainly that the appraisal of a project does not need to justify its programme, and the appraisal of a programme does not need to justify its portfolio. That is correct, and it is also why the portfolio, which sets the size of everything below it, is the one level no appraisal is required to justify.

    7 min read · Read
  5. 01.0501 Inception & Development

    The largest contributor to optimism bias is the document that starts the project

    HM Treasury publishes uplifts by project type, from 24% on a standard building to 200% on equipment and software. The instruction is to start at the upper bound and come down only against verified evidence. The single largest contributory factor it names is not the contractor, the ground or the weather.

    7 min read · Read
  6. 01.0601 Inception & Development

    Weighting and scoring is the method the guidance warns against

    The standard option appraisal is a table. Options down the side, criteria across the top, weights, scores, a total, a winner. The Green Book names that technique and recommends against it, on the grounds that it lacks an objective basis and reduces transparency. What it recommends instead does not rank options at all. It builds them.

    7 min read · Read
  7. 01.0701 Inception & Development

    Whether it was worth doing is the least evaluated question

    The UK government reviewed evaluation across the 227 largest projects it runs, together worth £834 billion. A third have a plan capable of finding out whether they worked. Of the three kinds of evaluation, the one asking whether the benefits justified the cost is the weakest, and the reason is that it has to be designed before the project starts.

    7 min read · Read
  8. 01.0801 Inception & Development

    A gate that has never been failed is not a control

    Assurance before anything is built costs less and changes more than assurance anywhere else in the lifecycle. It is also the assurance that is hardest to buy, and the reason is not that owners are careless. It is that inception produces very little of the sort of evidence an assurance function knows how to examine.

    7 min read · Read
  9. 01.0901 Inception & Development

    An estimate is a measure of how well the scope is defined

    Early cost estimates are produced as ranges and quoted as commitments. The classification systems behind them say something narrower and more useful. Accuracy is governed by the maturity of the scope definition, and the published ranges exclude the project types a large mixed-use development is made of.

    8 min read · Read

Stage 02

Delivery & Controls

Governance, cost, schedule and risk during construction, and the difference between progress and health.

The stage
  1. 02.0102 Delivery & Controls

    An extension of time is tested against records made during the delay

    A claim for more time turns on three separate questions. Was the contract's notice procedure satisfied? Is the event one for which the contract allows an extension, or whose risk it otherwise places on the employer? Did it actually delay completion? Money is a separate claim, with its own proof of causation and amount. Each question is later tested against what was written down while the event was happening, by whichever party has to prove the point. Records do not create entitlement, a record of an event does not prove that it delayed completion, and the prevention principle does not rescue a claim under every contract or every governing law.

    14 min read · Read
  2. 02.0202 Delivery & Controls

    The score that is not a number

    A technical score on a qualitative criterion records what evaluators judged. The weighting decides how much of the award that judgement controls; it does not turn the judgement into a measurement. What makes the score answerable is a record that a reader outside the room can test against the solicitation and the proposal, and the instruments examined here require different parts of that record.

    9 min read · Read
  3. 02.0302 Delivery & Controls

    Three award rules make you disclose how the criteria are weighed. None makes you defend it.

    The WTO agreement, the UNCITRAL Model Law and the EU directive all require the relative importance of the evaluation criteria to appear in the tender documents. None says what the weighting should be, and the Model Law's own commentary calls it discretionary. The GPA and the Model Law specify the arithmetic completely in exactly one situation, an electronic auction, where a machine does the ranking. Meanwhile a 70/30 split under the World Bank's own price formula prices one technical point at 3.4% of the contract and puts a 30 point quality lead beyond the reach of any price at all.

    12 min read · Read
  4. 02.0402 Delivery & Controls

    Private projects overrun too. The difference is who counts.

    Government projects are said to run late and over budget while private ones finish. A 2004 study, using what its authors described as the largest dataset of its kind at the time, tested ownership statistically and found privately owned bridges and tunnels escalated more on average than publicly owned ones; its authors called the conventional view an oversimplification. What differs is not the outcome. It is who is counted, and what a private owner has that a public one does not, which is structure rather than virtue.

    15 min read · Read
  5. 02.0502 Delivery & Controls

    The payment chain is a loan, and the contractor is the lender

    A monthly certificate under Saudi Article 109 takes 80 days as the regulation is written, 86 on a real calendar with every office on time, and 128 if one payment order is returned at the wrong moment. On a programme of 1.2bn a year that is 283m to 421m of the contractor's own money standing in the project permanently, borrowed at the contractor's rate, and priced back into the tender. No rule names it, and nothing in the chain prices it.

    25 min read · Read
  6. 02.0602 Delivery & Controls

    Reliability can be specified like mass. Building owners do not.

    The committee that writes the world's dependability standards says reliability should be specified the way dimensions and mass are. Rail has had a published process for specifying and demonstrating it since 2002. The buildings sector's reference specification for what a contractor hands over asks for the manufacturer's projection of how many hours a repair will take, and never how often one will be needed.

    10 min read · Read
  7. 02.0702 Delivery & Controls

    The certified value and the booked value are two different records

    While a project is being built, its cost lives in two places. The project keeps a record of what has been built and certified. Finance keeps a record of what has been booked. The standards assume they agree. The only thing that makes them agree is a reconciliation, and one auditor has spent 27 years documenting what happens when it is not run.

    11 min read · Read
  8. 02.0802 Delivery & Controls

    A dashboard computed from your own beliefs is not information

    The test for any instrument on a capital programme is whether its output contains something the inputs did not. A rule applied, a calculation done, a source consulted. A rating a team gives itself contains none of these, and colouring it does not add one. One public dashboard has carried both kinds side by side since 2009, and an auditor has re-rated the self-assessed column and published the result.

    10 min read · Read
  9. 02.0902 Delivery & Controls

    Moving a date is not the same as re-planning

    When a programme slips, the recovery plan is usually the old plan with later dates on it. That is a translation, not a calculation, and it omits what the evidence says the extension itself costs. A large study of major construction found that each extra year of implementation correlates with cost overrun rising by 4.64%, and a plan that only moves dates has not applied it.

    9 min read · Read
  10. 02.1002 Delivery & Controls

    The ground was always there. The record was not.

    Unforeseeable physical conditions is a contract mechanism, not an explanation. The utilities under a site were installed by somebody who holds a record of them, and that record fails to reach the design for a structural reason. The organisation holding it does not bear the cost of it being wrong. Britain priced that failure at 2.4 billion pounds a year before building a national register to fix it.

    9 min read · Read
  11. 02.1102 Delivery & Controls

    Every programme performs well against a baseline it can move

    A government builder completed 36 major construction projects and routinely met its cost and schedule goals. It had rebaselined 25 of them, and its reports did not say so. When asked why they had moved a baseline, 4% of project managers gave their own cost or schedule performance as the reason.

    9 min read · Read
  12. 02.1202 Delivery & Controls

    The critical path cannot show a delay nobody scheduled

    A programme schedule is required to contain the owner's activities as well as the contractor's. A schedule that contains only the contractor's, with the owner's approvals and decisions shown as single milestones or not at all, is incomplete. An incomplete network does not produce an approximate critical path. It produces an invalid one, and it is invalid in a direction that always favours the same party.

    8 min read · Read
  13. 02.1302 Delivery & Controls

    Your contingency and their contingency are different money

    Two bodies an owner is likely to cite define contingency and management reserve in opposite directions. One says contingency is for unknown unknowns and sits with the owner. The other treats it as the allowance for what experience says will happen. Both are defensible, and an owner and a contractor using the word across a table are frequently discussing different money, held by different people, against different risks.

    7 min read · Read
  14. 02.1402 Delivery & Controls

    A forecast that never moves is not stable, it is unexamined

    Delivery assurance measures progress against a baseline. Testing the baseline is a different exercise, and it is the one the monthly report does not contain. A forecast that holds flat and then steps was not stable, it was unexamined, and two numbers usually available in an afternoon will show which.

    6 min read · Read
  15. 02.1502 Delivery & Controls

    You can place the activity outside. You cannot place the accountability there

    Clause 8.3 was retitled in the 2024 edition from Outsourcing to externally provided processes, products, technologies and services. The committee says the requirements did not substantially change. The four nouns still describe a category of arrangement wider than what outsourcing usually names, and the wider category is the one nothing in the audit plan is pointed at.

    7 min read · Read
  16. 02.1602 Delivery & Controls

    Programme risk is not the sum of its functions

    A capital programme does not simply contain larger versions of procurement, payment and resourcing. It creates chains that run through all of them, and a chain belongs to no function. That makes under-coverage a design problem in the audit plan rather than a question of materiality, and it has a method attached.

    11 min read · Read
  17. 02.1702 Delivery & Controls

    Engaging an engineer satisfies the standard. Deferring to one does not.

    The 2024 Standards require an internal audit function to obtain the competencies it does not have, which reads as permission to bring in an engineer. That is the easy half. The obligations that decide whether the exercise was worth commissioning all start after the engineer has arrived.

    7 min read · Read

Stage 03

Handover & Transition

The seam where information, accountability and intent change hands.

The stage
  1. 03.0103 Handover & Transition

    A delivered file is not an accepted record

    A handover contract can test that the information arrived and that the Engineer had no objection to it. That proves receipt. It does not prove that the data passed a schema, that its identifiers reconcile with the finance and maintenance records, or that the receiving system can run a transaction on it. Those are three further tests, and where a contract's information conditions end at delivery and absence of objection, each can fail while those information obligations are performed in full.

    13 min read · Read
  2. 03.0203 Handover & Transition

    The project crosswalk reaches capitalisation. What survives it?

    NASA requires a project work breakdown structure to correlate exactly through seven levels to the financial accounting structure, and EXPRO's cost and commitment procedure reconciles the project cost report to the corporate general ledger on a named form with a named owner. Both requirements are scoped to the project. The Saudi Ministry of Finance's asset manual then has finance allocate the project's cost to assets and components at capitalisation. None of the public documents reviewed here says the project's identifiers stay on the asset record after that.

    17 min read · Read
  3. 03.0303 Handover & Transition

    The evidence finance needs is in a file finance never sees

    Accounting asks one question at handover, whether the asset is capable of operating as management intended, and answers it with a certificate written for a different purpose. The document that actually tests capability, against the owner's stated requirements, with dates and measurements, is the commissioning file. The two are produced for different purposes and routed to different functions, so they do not meet.

    6 min read · Read
  4. 03.0403 Handover & Transition

    The only test the building ever gets

    Commissioning is the one assurance instrument that measures instead of reads. The standards that require it price its independence in tiers, publish their reasons, and there is a 1,500-building dataset that says what the money buys. It also says less than it used to, which is worth understanding rather than hiding.

    11 min read · Read
  5. 03.0503 Handover & Transition

    Operational readiness has seven conditions. Handover delivers two.

    The phrase travels across an office move, a production line, a hospital wing and a finance function taking on a new reporting basis, and it survives the journey by meaning nothing specific in any of them. ISO 55001 already makes it specific, and the arithmetic that falls out is uncomfortable.

    7 min read · Read
  6. 03.0603 Handover & Transition

    The date a project becomes an asset is not the date on the certificate

    There is a moment when a capital project stops being expenditure and starts being an asset, and it is an accounting entry with a date on it. The standard sets a capability test for that date. Practice mostly uses whichever certificate is nearest, and the two are not the same day.

    8 min read · Read
  7. 03.0703 Handover & Transition

    Completion describes the asset. Readiness describes the owner.

    Commissioning is the one handover instrument that tests rather than documents, and it tests the building against the owner's stated requirements. Everything on the other side of the boundary, whether the owner can actually run the thing, has no instrument that tests it, no budget line of its own, and no place on the critical path.

    7 min read · Read
  8. 03.0803 Handover & Transition

    Under FIDIC, taking over comes before acceptance

    Under FIDIC 2017, taking over and contractual acceptance of the works are separate. At taking over the owner takes possession and may begin operating; Sub-Clause 11.9 makes the Performance Certificate the document that constitutes acceptance, and it follows a Defects Notification Period of one year unless the Contract Data states otherwise. A general law-firm summary lists what can change at practical completion or taking over: the contractor's insurance of the works ends, the risk of loss transfers, exposure to delay damages stops, and, where the contract provides for it, retention and the performance bond can begin to release. Where they do, much of the hold on the contractor loosens just as the owner's exposure begins.

    9 min read · Read
  9. 03.0903 Handover & Transition

    At handover, every review arrives after the leverage has gone

    Assurance at this stage is triggered by the event that ends the ability to do anything about it. A review three months before taking over can still change what gets produced. The same review afterwards can only describe what is missing, and describing what is missing is not assurance, it is an inventory of the loss.

    6 min read · Read
  10. 03.1003 Handover & Transition

    Knowledge has a departure date

    Clause 7.7 is new in the 2024 edition and it is the one requirement with a deadline the others do not have. Knowledge is held by people, people leave, and on a programme moving from delivery to ownership the people holding it are employed by somebody else on a contract that is ending.

    7 min read · Read
  11. 03.1103 Handover & Transition

    The competence you need is not in the asset management function

    Clauses 7.1 to 7.4 read like human resources boilerplate and get skipped on the way to the interesting parts. They are where the system either becomes real or stays a document, because the decisions that determine asset outcomes are taken in finance, procurement and operations.

    7 min read · Read
  12. 03.1203 Handover & Transition

    Handover is where the cost lands, and the Gulf is now taking delivery

    The gap between what a contractor delivers and what an owner can operate has been measured properly once, more than 20 years ago and on another continent. Of the 15.8bn a year it found, 9.0bn fell on owners and operators, after everyone else had gone. The region now taking delivery at scale has no equivalent number.

    9 min read · Read

Stage 04

Operations & Asset Management

Knowing what you own, where it is, what condition it is in, and what it will cost to keep.

The stage
  1. 04.0104 Operations & Asset Management

    The land is on the books. Its location is held somewhere else

    A Saudi government entity can control land without holding a record that places it on the ground. The deed or allocation, the approved plan, the registered map and the valuation report are issued and kept by different bodies, and land described by plan, plot and stated lengths was not fixed in coordinates when its deed was written. Accrual accounting requires the carrying amount to be tied to a parcel whose location and area can be defended. This piece sets out where each record sits, three ways a description can put land in the wrong place, and when a corrected location is a restatement rather than a new estimate.

    16 min read · Read
  2. 04.0204 Operations & Asset Management

    What capital figures record, and what they leave elsewhere

    Gross fixed capital formation records the fixed assets acquired in a year, less disposals; in plain terms, investment spending. It does not measure what an asset is worth, what has been completed or what has entered service. Across the asset's lifecycle, its operation, maintenance, information, replacement and eventual disposal are governed and recorded under different rules, in budgets, registers, contracts and accounting records. What the figures show, what they cannot show, and where to look for the rest.

    9 min read · Read
  3. 04.0304 Operations & Asset Management

    Conformance is not maturity, and the body that says so is selling nothing

    Twelve national asset management societies agreed a position statement that says conformance to ISO 55001 may not deliver the value stakeholders want. It names four levels and publishes the characteristics of a mature organisation. It says it is not itself an assessment tool, points to companion guidelines for assessing maturity, and expects each member society to write its own detailed guidance. An owner is better off knowing whose scale produced a maturity score than buying the first ladder they are offered.

    6 min read · Read
  4. 04.0404 Operations & Asset Management

    Nobody will give you a deterioration curve

    Three global bodies govern how infrastructure is meant to be maintained, and each publishes the shape of the calculation without the numbers that make it run. ISO gives a seven-factor equation and says it will not tell you the factors. The World Road Association's free manual on deterioration models is two paragraphs long and points you at your own records. The owner is told the curve decides when to intervene, and is handed no curve. The organisation that solved this owns over 165,000 buildings, and it did not find a curve. It built something that generates one.

    10 min read · Read
  5. 04.0504 Operations & Asset Management

    A lighting pole in the desert is not an asset

    Componentisation is usually run as a decomposition exercise, and on a large estate a decomposition exercise has no natural end. The question that stops it is not how deep to go but what the asset is. A pole delivers nothing on its own; a road delivers a service, and the pole is part of it. Depth then follows from criticality and from what a payment mechanism has to measure.

    14 min read · Read
  6. 04.0604 Operations & Asset Management

    Counting desks while the useful life goes unexamined

    An entity holding 20bn of real estate sends teams to tag and depreciate 50m of chairs and monitors. The whole annual depreciation of that furniture moves the balance sheet by 0.036%. The 50-year life sitting under the real estate moves it by 100m if it is wrong by a decade, and the standard requires that judgement to be revisited every year.

    8 min read · Read
  7. 04.0704 Operations & Asset Management

    An entity is asked for four asset registers and builds one

    Where does a desk go? The question sounds trivial and it is not, because a Saudi public entity is asked to hold several registers of the same estate by two different authorities, built on two different organising principles. They are not in conflict. They are in sequence, and treating them as simultaneous is what produces the exercises everybody complains about.

    9 min read · Read
  8. 04.0804 Operations & Asset Management

    A strategic asset management plan that has never stopped anything is a description

    Clause 6.2.1 gave the SAMP its own requirement in the 2024 edition, and ISO strengthened the leadership clause in the same revision. The two changes belong together. A plan only allocates if somebody senior enough is willing to let it decline something, and a plan that has never declined anything has not been asked to allocate.

    9 min read · Read
  9. 04.0904 Operations & Asset Management

    Audited on the transactions, unaudited on the basis

    Where an internal audit function covers the asset base at all, it usually covers maintenance spend and procurement compliance, because those resemble the rest of the audit universe. The decision framework, the plan and the data go unexamined. The organisation ends up assured about how it spends and unassured about what it decided to spend on.

    6 min read · Read
  10. 04.1004 Operations & Asset Management

    Every organisation has a risk register. Ask for the other one

    The 2024 edition separated actions to address risk from actions to address opportunities, which the 2014 edition ran together in a single subclause. That is not a drafting tidy. When one process has to serve both, loss avoidance wins, because it is the half with a committee, a template and an auditor.

    9 min read · Read
  11. 04.1104 Operations & Asset Management

    ISO 55001 now requires you to write down how you decide

    Clause 4.5 is new in the 2024 edition and asks for three things, a decision-making framework, the criteria, and the methods. Knowing roughly how things get settled is not the same as being able to produce them, and an option appraisal nobody can audit is not a decision. It is a preference with a spreadsheet attached.

    9 min read · Read
  12. 04.1204 Operations & Asset Management

    ISO 55001 tells you what to build. It will not tell you what to build first

    The standard states in its own introduction that the order of its requirements implies no order of implementation. That is a defensible position for a standards committee and an expensive one for an organisation standing up an asset management function under compliance pressure.

    9 min read · Read
  13. 04.1304 Operations & Asset Management

    Nothing tells you when a record stopped being true

    In the 2024 edition Clause 7.6 is data and information, revised and set beside documented information at 7.5. Controlling a record and knowing it is still true are different questions. It is the difference between holding a register and being able to defend one.

    8 min read · Read
  14. 04.1404 Operations & Asset Management

    Operational control now says life cycle management, which is a larger change than it looks

    ISO listed it among the main differences from the 2014 edition, in the flattest language available. The clarification places life cycle management explicitly within operational planning and control.

    6 min read · Read
  15. 04.1504 Operations & Asset Management

    Preventive became predictive, and the second needs three things the first did not

    ISO renamed Clause 10.3 and fully technically revised it, which moves the question from whether to intervene to when. That is a different discipline requiring condition data, a view of how things deteriorate, and a funding mechanism that can act before anything has failed. Without all three, running to failure gets described as risk-based.

    7 min read · Read
  16. 04.1604 Operations & Asset Management

    You cannot buy an outcome you cannot specify

    Performance-based maintenance contracts move an owner from paying for activity to paying for a service level. That only works if the owner can already say what it owns, what condition it is in, and what keeping it there should cost. Where it cannot, the risk is not transferred. It is priced back.

    6 min read · Read
  17. 04.1704 Operations & Asset Management

    Accrual conversion gave three years. It did not give anyone a register.

    IPSAS lets a first-time adopter defer recognising its assets while it builds a reliable basis for measuring them. The relief is a runway. A programme procured to produce a valuation, rather than to build a function, arrives at the end of it with a number and no way to keep one.

    10 min read · Read

The full list

Every article, by stage

Or enter by what you are answerable for: the role entry points gather this writing behind the standard an auditor, an accountant or a cost controller already works under.

01 Inception & Development 9 articles

  1. 01.01Operations is told to take part in the business case. Nobody asks it to sign.16 min read ·
  2. 01.02A lifecycle ratio nobody can check, and a conclusion that does not need it7 min read ·
  3. 01.03Doing the project right, and doing the right project7 min read ·
  4. 01.04Every appraisal can be right and the portfolio still wrong7 min read ·
  5. 01.05The largest contributor to optimism bias is the document that starts the project7 min read ·
  6. 01.06Weighting and scoring is the method the guidance warns against7 min read ·
  7. 01.07Whether it was worth doing is the least evaluated question7 min read ·
  8. 01.08A gate that has never been failed is not a control7 min read ·
  9. 01.09An estimate is a measure of how well the scope is defined8 min read ·

02 Delivery & Controls 17 articles

  1. 02.01An extension of time is tested against records made during the delay14 min read ·
  2. 02.02The score that is not a number9 min read ·
  3. 02.03Three award rules make you disclose how the criteria are weighed. None makes you defend it.12 min read ·
  4. 02.04Private projects overrun too. The difference is who counts.15 min read ·
  5. 02.05The payment chain is a loan, and the contractor is the lender25 min read ·
  6. 02.06Reliability can be specified like mass. Building owners do not.10 min read ·
  7. 02.07The certified value and the booked value are two different records11 min read ·
  8. 02.08A dashboard computed from your own beliefs is not information10 min read ·
  9. 02.09Moving a date is not the same as re-planning9 min read ·
  10. 02.10The ground was always there. The record was not.9 min read ·
  11. 02.11Every programme performs well against a baseline it can move9 min read ·
  12. 02.12The critical path cannot show a delay nobody scheduled8 min read ·
  13. 02.13Your contingency and their contingency are different money7 min read ·
  14. 02.14A forecast that never moves is not stable, it is unexamined6 min read ·
  15. 02.15You can place the activity outside. You cannot place the accountability there7 min read ·
  16. 02.16Programme risk is not the sum of its functions11 min read ·
  17. 02.17Engaging an engineer satisfies the standard. Deferring to one does not.7 min read ·

03 Handover & Transition 12 articles

  1. 03.01A delivered file is not an accepted record13 min read ·
  2. 03.02The project crosswalk reaches capitalisation. What survives it?17 min read ·
  3. 03.03The evidence finance needs is in a file finance never sees6 min read ·
  4. 03.04The only test the building ever gets11 min read ·
  5. 03.05Operational readiness has seven conditions. Handover delivers two.7 min read ·
  6. 03.06The date a project becomes an asset is not the date on the certificate8 min read ·
  7. 03.07Completion describes the asset. Readiness describes the owner.7 min read ·
  8. 03.08Under FIDIC, taking over comes before acceptance9 min read ·
  9. 03.09At handover, every review arrives after the leverage has gone6 min read ·
  10. 03.10Knowledge has a departure date7 min read ·
  11. 03.11The competence you need is not in the asset management function7 min read ·
  12. 03.12Handover is where the cost lands, and the Gulf is now taking delivery9 min read ·

04 Operations & Asset Management 17 articles

  1. 04.01The land is on the books. Its location is held somewhere else16 min read ·
  2. 04.02What capital figures record, and what they leave elsewhere9 min read ·
  3. 04.03Conformance is not maturity, and the body that says so is selling nothing6 min read ·
  4. 04.04Nobody will give you a deterioration curve10 min read ·
  5. 04.05A lighting pole in the desert is not an asset14 min read ·
  6. 04.06Counting desks while the useful life goes unexamined8 min read ·
  7. 04.07An entity is asked for four asset registers and builds one9 min read ·
  8. 04.08A strategic asset management plan that has never stopped anything is a description9 min read ·
  9. 04.09Audited on the transactions, unaudited on the basis6 min read ·
  10. 04.10Every organisation has a risk register. Ask for the other one9 min read ·
  11. 04.11ISO 55001 now requires you to write down how you decide9 min read ·
  12. 04.12ISO 55001 tells you what to build. It will not tell you what to build first9 min read ·
  13. 04.13Nothing tells you when a record stopped being true8 min read ·
  14. 04.14Operational control now says life cycle management, which is a larger change than it looks6 min read ·
  15. 04.15Preventive became predictive, and the second needs three things the first did not7 min read ·
  16. 04.16You cannot buy an outcome you cannot specify6 min read ·
  17. 04.17Accrual conversion gave three years. It did not give anyone a register.10 min read ·

The map

What is joined to what.

Four catalogues of published material, joined by relationships declared in the content itself.