
What follows the certificate, and when
Enter one completion or taking-over date and get every consequential date under your contract regime, each computed from the clause that sets it.
The seam
The certificate issued at completion and the contractual dates the owner must then administer: the defects period, retention releases and the end of the contractor’s liability.

The instrument
Start here
Find the line that describes your contract. If none of them does, use Your own contract at the foot of the list and enter your own periods.
- It says FIDIC, and it was signed before about 2018
- FIDIC 1999. Check the cover of the conditions rather than the date of the project: the edition is printed on it.
- It says FIDIC, and it was signed from about 2018
- FIDIC 2017, but confirm on the cover. The 1999 edition is still being let on new work across this region.
- A Saudi government contract
- Saudi GTPL. Use the superseded 2006 law entry only if the contract was concluded before 1 December 2019.
- Amended FIDIC, a bespoke developer form, or you are not sure
- Take the nearest standard form and replace each period with the one your contract states. Every row below accepts a figure.
The periods, the names of the events and what hangs off them are different in each. Pick the wrong one and every date below is wrong.
Conditions of Contract, second edition 2017, Red and Yellow Books
The default on internationally procured infrastructure and building work, and the basis of most Gulf public contracts.
Sub-Clause 10.1. Not the date the building was finished, and not the date operations began.
What follows the certificate
projects-advisors.com/tools/handover-dates
- Contract regime
- FIDIC 2017
- Date on the Taking-Over Certificate
- not entered
FIDIC 2017
No dates yet
Each period here is cited to its clause and linked to free published commentary on that clause. Check your Contract Data and any Particular Conditions: every one of these periods can be amended, and on most Gulf contracts at least one has been.
Enter the date on the taking-over certificate above and every date below fills in.
Contractor can claim the first half of retention
awaiting the date
FIDIC 2017 Red Book, Sub-Clause 14.9: once the Taking-Over Certificate is issued, or deemed issued under Sub-Clause 10.1, the contractor includes the first half of the Retention Money in a Statement. The Engineer certifies it in the next IPC, or the FPC where the 2022 amendment applies, and the employer then pays under Sub-Clause 14.7. The date here is when that Statement can be submitted, not when the money is paid.
Defects Notification Period expires
awaiting the date
Override this with the period your Contract Data actually states. One year is the fallback, not the norm.
FIDIC Conditions of Contract, 2017 edition, Sub-Clause 1.1.27: the DNP is the period stated in the Contract Data, or one year if none is stated. Sub-Clause 11.1 runs the contractor’s obligation to remedy defects to that date.
Furthest the Defects Notification Period can be extended to
awaiting the date
FIDIC Conditions of Contract, 2017 edition, Sub-Clause 11.3: an extension may not carry the DNP more than two years beyond the expiry of the period stated in the Contract Data, and in 2017 an extension is available only where the defect results from an act listed in Sub-Clause 11.2(a) to (d).
Performance Certificate falls due
awaiting the date
In the 2017 Red Book the information condition is still only the Contractor’s Documents: the Notice of No-objection to the as-built records belongs to taking over, under Sub-Clause 10.1, so the asset information is on the critical path to the Taking-Over Certificate rather than to this one. The 2017 Yellow and Silver Books differ, adding that Notice to Sub-Clause 11.9.
FIDIC Conditions of Contract, 2017 edition, Sub-Clause 11.9: the Performance Certificate is deemed issued if the Engineer has not issued one within 28 days of the DNP expiring and the Contractor’s Documents being supplied.
A deemed Performance Certificate takes effect
awaiting the date
FIDIC Conditions of Contract, 2017 edition, Sub-Clause 11.9: a deemed Performance Certificate comes into effect a further 28 days after it is deemed issued.
Contractor can claim the second half of retention
awaiting the date
FIDIC 2017 Red Book, Sub-Clause 14.9: expiry of the latest applicable Defects Notification Period triggers the contractor’s Statement for the second half of retention. The Engineer then certifies the amount in the next IPC, or the FPC where the 2022 amendment applies, and may withhold the estimated cost of Clause 11 work still outstanding; payment follows under Sub-Clause 14.7. The Performance Certificate is not the trigger. The date here is when that Statement can be submitted, not when the money is paid. The sequence is set out in High-Point Partnership, Some Important Timelines in the FIDIC 2017 Red Book, Part II, page 7, and FIDIC’s 2022 amendments add the FPC to Sub-Clause 14.9.
Contractor’s right of access to the site ends
awaiting the date
FIDIC Conditions of Contract, 2017 edition, Sub-Clause 11.7: the right of access extends to 28 days after issue of the Performance Certificate, where under the 1999 edition it ended on issue.
Liability for Plant ends
awaiting the date
FIDIC Conditions of Contract, 2017 edition, Sub-Clause 11.10: liability for unfulfilled obligations in respect of Plant is limited to two years after the DNP for that Plant ends, unless the law provides otherwise or in cases of fraud, gross negligence, deliberate default or reckless misconduct.
Computed from
- Tyson, FIDIC 2017: Clause 11, Defects After Taking Over, Howard Kennedy (FIDIC 2017 second edition, clause commentary; read 2026-09-25)https://internationalconstructionknowledgehub.com/wp-content/uploads/VT-FIDIC-2017-Clause-11-Defects-After-Taking-Over.pdf
- Saudi Government Tenders and Procurement Law and its Executive Regulations, consolidated Arabic text, third edition (third edition, the law in force until the new law takes effect; amendments to the regulations after this edition are not consolidated in it; linked as the Internet Archive’s copy of 1 October 2026 since the Ministry moved its site; read 2026-11-02)https://web.archive.org/web/20261001111156/https://www.mof.gov.sa/Knowledgecenter/newGovTendandProcLow/Documents/%D8%B1%D8%A8%D8%B7%20%D9%86%D8%B8%D8%A7%D9%85%20%D8%A7%D9%84%D9%85%D9%86%D8%A7%D9%81%D8%B3%D8%A7%D8%AA%20%D9%88%D8%A7%D9%84%D9%85%D8%B4%D8%AA%D8%B1%D9%8A%D8%A7%D8%AA%20%D8%A7%D9%84%D9%84%D8%A7%D8%A6%D8%AD%D8%A9%20%D8%A7%D9%84%D8%AA%D9%86%D9%81%D9%8A%D8%B0%D9%8A%D8%A9%20-%20%D8%A7%D9%84%D8%A5%D8%B5%D8%AF%D8%A7%D8%B1%20%D8%A7%D9%84%D8%AB%D8%A7%D9%84%D8%AB.pdf
- Executive Regulations of the Government Tenders and Procurement Law (2019 Executive Regulations, amended 1 September 2026; to be re-issued with the new law; linked as the Internet Archive’s copy of 7 October 2026 since the Ministry moved its site; read 2026-11-02)https://web.archive.org/web/20261007212253/https://www.mof.gov.sa/en/Knowledgecenter/newGovTendandProcLow/Documents/Executive%20Regulations.pdf
- Saudi Government Tenders and Procurement Law, Royal Decree M/128 (Royal Decree M/128 (1440), in force from 1 December 2019; replaced from about 2 January 2027; linked as the Internet Archive’s copy of 1 October 2026 since the Ministry moved its site; read 2026-11-02)https://web.archive.org/web/20261001111153/https://www.mof.gov.sa/en/Knowledgecenter/newGovTendandProcLow/Documents/The%20Government%20Tenders%20and%20Procurement%20Law2.pdf
- Government Tenders and Procurement Law, new law published in Umm Al-Qura 22/3/1448 (4 September 2026), Arabic (gazetted 4 September 2026; in force 120 days after publication; read 2026-09-05)https://www.uqn.gov.sa/decisions-and-regulations/4001762
- NEC, Defining and managing defects in the ECC (NEC4; read 2026-09-03)https://www.neccontract.com/news/defining-and-managing-defects-in-ecc-and-liability-for-not-correcting-them
- JBCC Advisory Note 21.0, Defects Liability Period and Final Completion, edition 6.2 (JBCC Principal Building Agreement, current edition; read 2026-09-03)https://www.jbcc.co.za/advisory_notes/JBCC%20ADVISORY%20NOTE%2021.0_Defects%20before%20and%20after%20Final%20Completion%20Ed%206.2.pdf
Computed in your browser. Nothing you enter is sent to Projects Advisors or to anyone else.
What it takes, and what it gives
What you supply
- Contract regime
- The completion or taking over date
- Your own periods where the contract varies them
What you get
- A dated calendar of consequences, each with its clause
- A printable sheet for the warranty and defects file
Basis
What this computes from
Every document below is named in full. The link is a convenience on top of the citation.
All the sourcesRead the sources
- Tyson, FIDIC 2017: Clause 11, Defects After Taking Over, Howard Kennedy
FIDIC 2017 second edition, clause commentary; read 2026-09-25. Free. A clause-by-clause commentary that quotes the periods, including the two-year cap on extending the DNP. It also lists a Notice of No-objection to the as-built records as a new precondition to the Performance Certificate. That is the position in the 2017 Yellow and Silver Books, whose Sub-Clause 11.9 adds it. The 2017 Red Book differs: its Sub-Clause 10.1 makes the as-built and O&M No-objection conditions, where they apply, conditions of taking over, and its Sub-Clause 11.9 does not add that Notice. - Saudi Government Tenders and Procurement Law and its Executive Regulations, consolidated Arabic text, third edition
third edition, the law in force until the new law takes effect; amendments to the regulations after this edition are not consolidated in it; linked as the Internet Archive’s copy of 1 October 2026 since the Ministry moved its site; read 2026-11-02. Free in full, in Arabic, from the Ministry of Finance: each article of the 2019 Law printed beside the regulations that implement it, 117 pages. The enacted text on securities and receipt. Law Article 61(1) sets the final guarantee at 5% of the contract value within 15 working days of notice of the award, and 61(4) keeps it until the contractor has performed its obligations and the project is finally received. Regulations Article 101 requires the final guarantee to be extended in construction contracts where maintenance and warranty work runs «لما بعد انتهاء سنة الضمان المشار إليه في الفقرة (1) من المادة (الثامنة والعشرين بعد المائة)»; Article 111 pays a final statement of not less than 10% in public construction contracts after initial receipt; Article 128 sets a warranty period of not less than one year from initial receipt, keeps the warranty for shortcomings not dealt with at initial receipt, and makes final receipt follow the end of that period and the delivery of drawings, equipment specifications and project documents. - Executive Regulations of the Government Tenders and Procurement Law
2019 Executive Regulations, amended 1 September 2026; to be re-issued with the new law; linked as the Internet Archive’s copy of 7 October 2026 since the Ministry moved its site; read 2026-11-02. Free in full. Article 127 sets the receipt procedure, 128 a warranty period of not less than one year, 99 the ten-year liability, and 109 the payment chain. Note that the 2007 regulations of the superseded 2006 law are still hosted on the same site and number these provisions differently. Searched in the Arabic on 7 September 2026 for a late payment remedy: فائدة and فوائد, interest, appear zero times in the 117 pages of the law and its regulations. What exists instead is the claims route under Article 68 of the Law: the contractor files within 60 days of the event, the consultant reports within 21 days of a COMPLETE claim, the agency studies within 45, the committee under Article 86 decides within 45 of a complete claim, compensation is capped at 20% of the contract value and anything beyond that goes to the Administrative Court. So the contractor must initiate, evidence and win, where FIDIC 14.8 accrues charges automatically and without notice. Article 108, immediately before the payment chain, is the offset and was read in the Arabic on 7 September 2026: يجوز, may, not shall, the government authority MAY disburse an advance payment not exceeding 10% of the total contract value, against a bank guarantee equal to it, recovered from the contractor’s dues in instalments at a percentage equal to the advance percentage, from the value of each certificate, starting with the first. So the advance is discretionary, capped, costs a guarantee fee, and amortises to zero across the contract rather than standing as a buffer. - Saudi Government Tenders and Procurement Law, Royal Decree M/128
Royal Decree M/128 (1440), in force from 1 December 2019; replaced from about 2 January 2027; linked as the Internet Archive’s copy of 1 October 2026 since the Ministry moved its site; read 2026-11-02. Free in full from the Ministry of Finance, in English. Issued 16 July 2019, in force from 1 December 2019. - Government Tenders and Procurement Law, new law published in Umm Al-Qura 22/3/1448 (4 September 2026), Arabic
gazetted 4 September 2026; in force 120 days after publication; read 2026-09-05. Free in full, 101 articles, in the Official Gazette. Article 100 replaces Royal Decree M/128 (1440); Article 101 brings it into force 120 days after publication; Article 99 requires new Executive Regulations within the same period. Article 2 names life cycle cost, execution quality, operational efficiency and risk management among the law’s objectives. Article 59, read on 25 September 2026, keeps the final guarantee at 5% of the contract value, lodged within 15 working days of notice of the award and held until the contractor has performed its obligations and the project is finally received. Read on 5 September 2026. - NEC, Defining and managing defects in the ECC
NEC4; read 2026-09-03. Free, published by NEC itself. Gives the NEC4 clause numbers and the typical defects date, and says the defect correction period is stated in the Contract Data. - JBCC Advisory Note 21.0, Defects Liability Period and Final Completion, edition 6.2
JBCC Principal Building Agreement, current edition; read 2026-09-03. Free, published by JBCC. Quotes clauses 21.1, 21.12 and 22.1 in full, which is where the 90-day defects period and the five-year latent liability come from.
Cite this page
Projects Advisors, “What follows the certificate, and when,” revised 2026-11-02, https://projects-advisors.com/tools/handover-dates
What the output feeds
The next tool in the chain
Warranty register builder- Framework domain 03.3: Taking over, and what was waived to achieve it
The argument this tool tests
Under FIDIC, taking over comes before acceptance