Punch list

The list, made near completion, of work that is incomplete or does not conform to the contract, each item to be corrected and then checked off; also called a snag list.

A punch list records what an inspection near completion found not yet done or not yet conforming. The United States Unified Facilities Guide Specifications give a public, worked version in their quality control section: near completion of the work, the contractor’s quality control manager inspects it and develops a punch list of items that do not conform to the approved drawings, specifications and contract, each with an estimated correction date. Follow-on inspections confirm each correction before a pre-final inspection, which produces its own pre-final punch list, and then a final acceptance inspection.

The name and the contractual consequence depend on the form. Fenwick Elliott’s summary of practice under English law places the snagging or punch list alongside the practical completion certificate. FIDIC’s 2017 conditions carry the equivalent inside the Taking-Over Certificate: Sub-Clause 10.1, as quoted in a conference presentation published by FIDIC, allows minor outstanding work and defects that will not substantially affect safe use to be listed in the certificate.

A list records only what the inspection saw, and defects keep appearing after it. The Court of Appeal in Mears v Costplan, as Fenwick Elliott summarises it, held that latent defects cannot prevent practical completion, and the same summary states that a defects period is not an exclusive remedy unless the contract clearly says so, so the contractor remains liable for breaches during and after it. Saudi Arabia’s Executive Regulations make the point in their own terms. Article 128(2) provides «ولا يحول دون التزام المتعاقد بضمانها وصيانتها استلام الجهة للأعمال مع عدم إبداء ملاحظاتها عليها أو على ما يظهر من نواقص أو مواد مخالفة للمواصفات مما لم يتم تداركه أثناء الاستلام الابتدائي»: receiving the works without observations does not release the contractor from warranting and maintaining them against shortcomings not dealt with at initial receipt.

What secures correction after the list is closed depends on the contract and the regime that governs it. Jordan’s unified construction contract requires a defects remedy guarantee at taking over «لضمان قيامه باستكمال الأعمال المتبقية وتنفيذ أعمال إصلاح العيوب المطلوبة», to secure completion of the outstanding work and the remedying of defects for the stated period. Saudi procurement law keeps the final guarantee until the contractor has performed its obligations and the project is finally received. Other contracts use retention. Final receipt then verifies closeout rather than repeating the first inspection: under Article 128(4) of the Saudi regulations it follows the end of the warranty and maintenance period, the contractor’s performance of its obligations and its delivery of the drawings, equipment specifications and project documents. Defects found after initial receipt may differ from the outstanding items recorded there.

Sources

Unified Facilities Guide Specifications, UFGS 01 45 00, Quality Control, August 2026, paragraph 1.10, Completion Inspections, on the punch-out, pre-final and final acceptance inspections. Jatinder Garcha and Edward Colclough, Fenwick Elliott, Contractual liabilities post completion, 28 January 2021, slides 7, 8 and 11, for the punch list alongside the practical completion certificate, the summary of Mears Ltd v Costplan Services (South East) Ltd [2019] EWCA Civ 502, and defects periods not being an exclusive remedy. Cotovelea, Tsaturova and Glover, Differences between the Civil and Common Law, Part 2: Delay Damages and Taking-Over, a presentation published by FIDIC, slide 2, quoting Sub-Clause 10.1. Executive Regulations of the Government Tenders and Procurement Law, Article 128(2) and (4), in the consolidated Arabic text published by the Ministry of Finance. Jordan Ministry of Public Works and Housing, Unified Construction Contract 2010, second amended edition 2013, Instructions to Tenderers 5-2.

Cite this page

Projects Advisors, “Punch list,” revised 2026-11-02, https://projects-advisors.com/reference/punch-list