Payment chain calculator
Add up the payment periods in the rule that governs your contract, in the unit the rule is written in, and see the wait in calendar days and what financing it costs on every certificate.
The seamThe office that signs the payment order and the contractor financing the work until it clears. The days are the owner’s design and the cost of them arrives in the bid, so the owner pays for the chain without ever seeing a line for it.
This page does two things. It converts a payment rule to calendar days, which matters because these rules are written in different units and one of them, Article 109, uses both inside a single chain, so they cannot be compared as they stand. Then it prices the wait: the certificate value and the rate below are used to work out what financing the gap costs the contractor for one certificate, which is the figure that arrives in the bid.
The values are an example: the Saudi chain on a five-day week with no public holidays, which is where the 80 days comes from. Replace them with the rule and the calendar that govern your own contract. Nothing is uploaded; the arithmetic runs in this page.
Five published rules, each read at the document, or your own periods.
Only affects a rule written in working days. A calendar-day rule is unmoved by it.
Holidays that fall on what would otherwise be a working day. Left at zero the output is the rule's own arithmetic; raise it and the wait lengthens.
Where the rule restarts a period on a return. Only Article 109 does, of the five.
The sum being waited for: one monthly or provisional certificate. Drives every money figure below and nothing else; the days are unaffected by it.
1,000,000
What the wait is priced at. The rate the contractor borrows at, not the owner's, because it is the contractor carrying the certificate. That difference is the stated reason in Directive 2011/7/EU for capping public payment periods.
A label only. The arithmetic is the same in any currency, and this puts a unit beside the money figures so they do not have to be remembered.
Saudi Executive Regulations, Article 109. The only one of the five written in two units, and the only one that restarts a period when the payment order is returned.
Against a real calendar
The arithmetic above spreads the working week and the holidays evenly across the year, which is the only honest thing to do when comparing rules with no start date. Give a submission date and the chain runs against real days instead, which is where the mixed units show what they do: a holiday lengthens a period written in working days and leaves a period written in calendar days exactly where it was.
Holidays are yours to enter. Nothing here tracks an announcement or a moon sighting, and a holiday nobody typed in does not exist as far as this page is concerned.
The day the first office received the statement and its supporting documents. Every one of these rules gates its clock on completeness, so a package short of its evidence has not started anything. Leave empty to skip this section.
Saudi Arabia, and most of the Gulf, closes Friday and Saturday. This affects only periods written in working days.
Which day of the restarting period the document came back on. Zero models a clean run. This is the input that costs the most, because the period then runs again in full from resubmission.
How long the office that raised the payment order needs before it goes back. Working days, so a return that lands inside a holiday cannot be answered until the office reopens, which is where a chain quietly gains weeks.
Public holidays
None entered, so the chain stops only for the weekend.
The preset is the 1446 pair on the official Umm al Qura calendar: Article 127 of the civil service HR regulations closes government offices from the 25th of Ramadan to the end of the 5th of Shawwal, and from the 5th to the 15th of Dhu al Hijjah, while the Labour Law gives an employee of a private firm four days at each. Under Article 109 the supervising consultant is the private firm and the agency is the government office, so one certificate passes two doors that are shut for different lengths of time. Check the dates against what your own offices announced, and type those instead if they differ.
Payment chain calculator
2026-10-01. projects-advisors.com/tools/payment-chain
- Rule
- Saudi Executive Regulations, Article 109
- Working week, for the comparable figure
- 5 days, 0 public holidays a year
- Returns modelled, for the comparable figure
- 0
- Certificate value
- 1,000,000
- Cost of money
- 8% a year
- Submission date, which drives the dated run
- not entered, so the dated run is off
- Holiday dates, which drive the dated run
- none
- Return modelled on the dated run
- none
From invoice to cash, every office on time
80 days from invoice to cash
25 working days and 45 calendar days, a chain in two units, with the working part converted on a 5-day week and no public holidays, in the rule as written. Every office meets its deadline in this figure, so it is the floor rather than the experience. One return of the payment order would add the whole of the last period again.
| Who holds the paper | As written | Calendar days | Cumulative |
|---|---|---|---|
| Consultant verifies on site and reports | 10 working days | 14 | 14 |
| Government agency approves and issues the payment order | 15 working days | 21 | 35 |
| Ministry pays (restarts on a return) | 45 calendar days | 45 | 80 |
What the wait costs, on one certificate
Financing 1,000,000 for 80 days at 8% a year costs 17,534.25, which is 1.75% of the certificate. A contractor who has read the rule can price that cost into the bid, and the FIDIC commentary listed below says longer payment periods raise contractors’ prices. An owner who has never computed it may be paying it without seeing a line for it.
The other published rules, in the same unit
| Rule | Calendar days | Yours is longer by | What those days cost |
|---|---|---|---|
| EU late payment directive 2011/7, Article 4 | 30 | +50 | 10,958.9 |
| UK Procurement Act 2023, section 68 | 30 | +50 | 10,958.9 |
| US federal prompt payment rule, 5 CFR 1315.4 | 30 | +50 | 10,958.9 |
| FIDIC Red Book 1999, Sub-Clauses 14.6 and 14.7 | 56 | +24 | 5,260.27 |
Your chain is compared at the total shown at the top, returns included, because a chain that restarts is the length it restarts to. The other rules are shown at zero returns, since none of the other four has a restart provision to apply, and that asymmetry is the finding rather than a distortion. A negative figure means the rule you chose is the shorter one.
Who bears the chain's own slowness
Three of the five rules put the cost of lateness on the party that owns the chain. FIDIC runs financing charges from the due date whether or not the certificate was issued on time, so an Engineer's lateness costs the Employer. The US rule pays interest automatically, without the contractor claiming it. The UK Act voids a term that stretches the period. Article 109 restarts its longest clock when a payment order is returned, which puts the cost of a query on the party that raised the invoice. None of that is in the arithmetic above, which assumes everybody is on time; it decides who pays when they are not.
What this page cannot tell you
Whether the chain is worth its length. What a longer chain buys is verification before public money leaves, and whether the second and third verifications catch what the first would not is an empirical question nobody has published an answer to. The figure that would settle it is how many payment orders the later offices returned last year, for what, and what the return was worth. This page will not supply a verdict in its place, because a rating would be an opinion with arithmetic attached to it.
It also cannot tell you what actually happens. No dataset of real payment times against any of these five rules was found, so nothing here says whether they are met in practice, on either side.
Periods read at the document 6 and 7 September 2026: Saudi Executive Regulations Article 109; FIDIC 1999 Sub-Clauses 14.6 and 14.7 via a published clause commentary; Directive 2011/7/EU Article 4; Procurement Act 2023 section 68; 5 CFR 1315.4. The 2019 Saudi law and its regulations are replaced by the law gazetted on 4 September 2026 when it takes effect, and whether the new regulations change Article 109 is a review owed by January 2027. The conversion from working days to calendar days is this page's arithmetic, not any rule's. Without a submission date it spreads the working week and the holidays evenly across a year, which is the only honest thing to do when comparing rules that have no start date between them. With one, it walks the calendar you entered, day by day, and that is the figure your certificate is paid on.
The period that runs after completion, rather than during it, is a different clock and has its own page: the handover date calendar computes the defects and warranty periods from the same law.
Computed from
- Executive Regulations of the Government Tenders and Procurement Law (2019 Executive Regulations, amended 1 September 2026; to be re-issued with the new law; read 2026-09-03)https://www.mof.gov.sa/en/Knowledgecenter/newGovTendandProcLow/Documents/Executive%20Regulations.pdf
- Saudi Government Tenders and Procurement Law, Royal Decree M/128 (Royal Decree M/128 (1440), in force from 1 December 2019; replaced from about 2 January 2027; read 2026-09-03)https://www.mof.gov.sa/en/Knowledgecenter/newGovTendandProcLow/Documents/The%20Government%20Tenders%20and%20Procurement%20Law2.pdf
- Government Tenders and Procurement Law, new law published in Umm Al-Qura 22/3/1448 (4 September 2026), Arabic (gazetted 4 September 2026; in force 120 days after publication; read 2026-09-05)https://www.uqn.gov.sa/decisions-and-regulations/4001762
- Tyson, FIDIC 1999 Red Book, Clause 14 Contract Price and Payment, clause commentary, International Construction Knowledge Hub (FIDIC 1999 first edition, clause commentary; read 2026-09-07)https://internationalconstructionknowledgehub.com/wp-content/uploads/Clause-14.pdf
- Directive 2011/7/EU on combating late payment in commercial transactions (OJ L 48, 23 February 2011; read 2026-09-07)https://eur-lex.europa.eu/LexUriServ/LexUriServ.do?uri=OJ:L:2011:048:0001:0010:EN:PDF
- Procurement Act 2023, section 68, implied payment terms in public contracts (as in force 24 February 2025; read 2026-09-07)https://www.legislation.gov.uk/ukpga/2023/54/section/68
- 5 CFR 1315.4, Prompt payment standards, Office of Management and Budget (eCFR, current to 3 September 2026; read 2026-09-06)https://www.ecfr.gov/current/title-5/chapter-III/subchapter-B/part-1315/section-1315.4
- Executive Regulations for Human Resources in the Civil Service, Saudi Arabia, Article 127 (as amended to 2024; read 2026-09-07)https://www.hrsd.gov.sa/sites/default/files/2024-05/%D8%A7%D9%84%D9%84%D8%A7%D8%A6%D8%AD%D8%A9%20%D8%A7%D9%84%D8%AA%D9%86%D9%81%D9%8A%D8%B0%D9%8A%D8%A9%20%D9%84%D9%84%D9%85%D9%88%D8%A7%D8%B1%D8%AF%20%D8%A7%D9%84%D8%A8%D8%B4%D8%B1%D9%8A%D8%A9.pdf
- Ministry of Human Resources and Social Development, Holidays and Leaves, Labour Law entitlements (authored 15 November 2019; read 2026-09-07)https://www.hrsd.gov.sa/en/knowledge-centre/articles/322