One of the four chillers. Its identifier, test record, warranty, register entry, components, service life, replacement and disposal belong here.
Chiller 04 is the same machine as on One asset, four records, which shows it through the four records that describe it at handover. One asset, four records
Entry in the technical asset register
- Entry Illustrative
- CH-04, under the chilled-water plant, with its serial number, its site test record and fixed asset 0041-002, the number finance uses for it.
- Warranty Illustrative
- The manufacturer’s equipment warranty runs 24 months from energisation, 11 weeks before taking over. The contractual defects period runs from taking over of Section 2 and is a separate obligation.
What the method says at this step
Enter each asset, and trace it to the project record and to the financial record in both directions.
Entries in the records DE-118 · The step in the method
Financial recognition and measurement
- Cost Illustrative
- Held in work in progress against package M3, certified at 14.2m in total; the four chillers’ share is identified from the subcontract’s schedule of rates, and the basis of that split is recorded.
What the method says at this step
Classify costs as eligible or not, and hold eligible costs as work in progress against identifiable items.
The step in the method
Cessation of capitalisation and transfer from work in progress
- Available-for-use date Illustrative
- Month 29, after the integrated plant test, two months before taking over of Section 2; the transfer from work in progress is recorded at that date.
- Components Illustrative
- Chiller 04 is capitalised as two components: the machine, and its controls.
What the method says at this step
The step in the method
Start of depreciation
- Useful lives Illustrative
- The machine 20 years, the controls 10 years, each with the basis for the life recorded, from month 29, when the chiller was available for use.
What the method says at this step
Under IPSAS 45, each part with a cost significant in relation to the total cost of the item is depreciated separately.
Required IPSAS 45, property, plant and equipment, paragraph 41Binding only where it is adopted or contracted
Entries in the records FB-05 · The step in the method
Renewal or replacement decision
- Operating year 11 Illustrative
- The controls fail and are replaced. The replacement is recorded as driven by failure rather than by plan, and the carrying amount of the old controls is derecognised.
What the method says at this step
Under IPSAS 45, when a part is replaced and the replacement meets the recognition criteria, the carrying amount of the replaced part is derecognised.
Required IPSAS 45, property, plant and equipment, paragraph AG14Binding only where it is adopted or contracted
Entries in the records FB-05 · The step in the method
Disposal and derecognition
- Operating year 24 Illustrative
- Chiller 04 decommissioned and removed with its refrigerant recovered; the register entry closed and the component derecognised, each recorded as its own event.
What the method says at this step
Decommission, remove the asset from the technical register and derecognise it in the accounts, each on its own record.
Entries in the records OB-12 · The step in the method