Skip to content
Reference

One asset, four records

A water-cooled centrifugal chiller, one of four serving a district office building, installed during the fit-out and energised 11 weeks before the building was taken over. Four systems hold a record of it. They disagree about how long it lasts, what one unit of it is, and when it started, and none of the disagreements is anybody's mistake.

Chiller 04 does not exist. The costs, dates and quantities below are illustrative and each is labelled; the rules and the service life data are sourced and each says where from. The example is deliberately ordinary: this is what a competent project produces, not a failing one.

01

Project

Calls it
Package M3, mechanical plant, line 14
Lives in
The cost report and the payment certificates
Kept by
The commercial team, until the final account closes
  • Cost recorded against

    Illustrative

    The mechanical subcontract, not the chiller

    The chiller appears in the subcontract’s schedule of rates, but the certified cost is a package total that includes installation, pipework and controls. This is ordinary practice and it is the decision that determines everything downstream.

  • Certified value, package M3

    Illustrative

    14.2m, of which the chillers are a schedule line

  • What the record can answer

    Illustrative

    How much was paid, to whom, and when

  • What it cannot answer

    Illustrative

    What this chiller cost, delivered and installed

    Not because anyone failed. The question was never asked while the records were open.

02

Engineering

Calls it
CH-04, chiller, water-cooled centrifugal
Lives in
The maintenance management system, asset hierarchy
Kept by
The maintenance manager
  • Maintainable items beneath it

    Illustrative

    11, including compressor, condenser bundle, evaporator, starter, controls

    Each is separately located, isolated and maintained. Two of them, the controls and the starter, will be replaced at least once inside the life of the machine.

  • Energisation date

    Illustrative

    11 weeks before taking over

    This is the date the warranty actually starts on most equipment, and it is why a warranty register built from the handover date is wrong by whatever the commissioning period was.

  • Observed service life, this equipment type

    Sourced

    25.2 years mean life for units replaced; 17.6 years mean age so far for units in service

    A distribution, not a number. The replaced units lived from 7 to 42 years, and that spread is the useful part, and it is what gets discarded when a single figure is copied onto a register.

    ASHRAE Service Life and Maintenance Cost Database, cooling equipment, chiller, centrifugal: 239 units reported, 209 in service (mean 17.6, median 18.0, standard deviation 8.2, range 3 to 41), 30 replaced (mean 25.2, median 25.0, standard deviation 7.6, range 7 to 42).

    Read the sources

    • ASHRAE Service Life and Maintenance Cost Databaselive database; read 2026-09-26.Free. Observed service lives from 345 buildings, reported as mean, median, standard deviation and range, separately for equipment still in service and equipment replaced. Built to supersede the 1978 Akalin survey table.
  • What the record can answer

    Illustrative

    What failed, what was done, what is due, and where it is

03

Finance

Calls it
Asset 0041-002, plant and machinery, HVAC
Lives in
The fixed asset register
Kept by
The financial controller
  • Recognised as

    Illustrative

    One asset, with two depreciated components

    The machine and the controls, split because their lives differ. The other nine maintainable items are inside the remainder, which IPSAS 45 paragraph 43 requires to be depreciated too.

  • Basis for splitting components

    Sourced

    Cost significant in relation to the total

    Significance is measured in money. A cheap component on a critical system is not significant under this test, however important it is to keeping the building open.

    IPSAS 45, Property, Plant, and Equipment, paragraph 41: each part of an item with a cost or value significant in relation to the total cost or value of the item shall be depreciated separately. Paragraph 42 permits parts with the same useful life and depreciation method to be grouped.

    Read the sources

  • Cost

    Illustrative

    An apportionment of the package total

    Because the project recorded cost by package. The apportionment is a reasonable estimate and it is the basis of a depreciation charge running for two decades.

  • Useful life assigned

    Illustrative

    20 years

    A round number, taken from a table. Against the ASHRAE distribution it is defensible; what matters is whether anyone recorded that it was a choice and reviewed it since.

  • Review obligation

    Sourced

    At least at each annual reporting date

    IPSAS 45, paragraph 48: the residual value and the useful life of an asset shall be reviewed at least at each annual reporting date, with any change accounted for as a change in an accounting estimate.

    Read the sources

04

Operations

Calls it
The chiller that trips in August
Lives in
The renewal plan, and the operators’ own knowledge
Kept by
The operations manager
  • Replacement interval planned

    Illustrative

    25 years, from the manufacturer’s guidance

    Five years longer than the life on the fixed asset register, for the same physical machine. Neither number is wrong on its own terms; they answer different questions and nobody has put them side by side.

  • What triggers replacement in practice

    Illustrative

    Failure rate, cost to keep, or no longer meeting the requirement

    Whichever arrives first. This is the only one of the four lives that is ever tested against the machine.

  • Evidence the accounting estimate may be wrong

    Sourced

    Held here, and rarely asked for

    The standard points at the operator for evidence that the register is wrong. The annual review at paragraph 48 is usually performed without asking them.

    IPSAS 45, paragraph 49: where maintenance policies exacerbate the wear and tear of an asset, its useful life should be reassessed and the asset tested for impairment as appropriate.

    Read the sources

Where the four records disagree

Three questions an owner would call simple. Each has more than one answer, and in each case the answers come from records that are individually correct.

How long does this chiller last?

  • Engineering

    25.2 years mean at replacement, range 7 to 42; in-service units 17.6 years old on average so far

  • Finance

    20 years

  • Operations

    25 years planned

Three answers to one question, and the disagreement is not an error. The observed figure is a distribution across a population; the financial figure is an estimate about availability to this entity; the planned figure is an intention. The failure is not that they differ, it is that they differ without anyone having compared them, so no one number carries the knowledge in the other two.

What is one unit of this asset?

  • Project

    Part of a package

  • Engineering

    11 maintainable items

  • Finance

    2 components and a remainder

The unit changes with the question. IPSAS 45 paragraph 8 declines to prescribe one and permits aggregation of insignificant items, so finance is not being lazy; the engineering breakdown is set by maintainability, so it is not being pedantic. What is usually missing is traceability between the two.

When did this asset start?

  • Engineering

    Energisation, 11 weeks before taking over

  • Project

    The Taking-Over Certificate

  • Finance

    When available for use

Three dates, and they are used for different things: the warranty runs from the first, the risk of loss and the defects period from the second, depreciation from the third. Where all three are recorded as the same date, at least two were copied, and the warranty is the one that quietly loses weeks.

Correspondence

If something here is wrong, that is worth more than agreement.

Material errors are corrected on the affected pages. Messages are used to reply, not to build a mailing list.

Write to the publication