
Earned value calculator
From planned value, earned value and actual cost, the variances and indices; add the budget at completion for the estimates at completion. Formulas shown and cited.
The seam
The cost controller and the forecast the finance team will book.

The instrument
Budgeted cost of the work scheduled to date.
Budgeted cost of the work actually performed to date.
What the work performed has actually cost.
The total budget. Needed for the forecasts.
Earned value calculator
projects-advisors.com/tools/evm
- Planned value
- not entered
- Earned value
- not entered
- Actual cost
- not entered
- Budget at completion
- not entered
To date
Enter three figures
Enter planned value, earned value and actual cost to see the indices; add the budget at completion for the forecasts.
| Measure | Formula | Value |
|---|---|---|
| Cost variance | EV - AC | n/a |
| Schedule variance | EV - PV | n/a |
| Cost performance index | EV / AC | n/a |
| Schedule performance index | EV / PV | n/a |
| EAC, cost efficiency continues | BAC / CPI | n/a |
| EAC, the rest runs to budget | AC + (BAC - EV) | n/a |
| EAC, cost and schedule efficiency persist | AC + (BAC - EV) / (CPI x SPI) | n/a |
| Estimate to complete | EAC (CPI basis) - AC | n/a |
| Variance at completion | BAC - EAC (CPI basis) | n/a |
| To-complete performance index | (BAC - EV) / (BAC - AC) | n/a |
| Percent complete | EV / BAC | n/a |
| Percent spent | AC / BAC | n/a |
Formulas as set out in the GAO Cost Estimating and Assessment Guide. The to-complete performance index says what cost efficiency the remaining work needs to finish on budget; a TCPI far above the CPI is a forecast that assumes a recovery nothing to date supports.
Every figure here is read off the schedule. Whether that schedule can carry a forecast is a question of how it is built, which the schedule logic check asks of the file itself.
Computed from
- GAO Cost Estimating and Assessment Guide, GAO-20-195G, March 2020 (GAO-20-195G, March 2020; read 2026-08-24)https://www.gao.gov/products/gao-20-195g
Computed in your browser. Nothing you enter is sent to Projects Advisors or to anyone else.
What it takes, and what it gives
What you supply
- Planned value
- Earned value
- Actual cost
- Budget at completion
What you get
- CV, SV, CPI, SPI, EAC, ETC, TCPI
Basis
What this computes from
Every document below is named in full. The link is a convenience on top of the citation.
All the sourcesRead the sources
- GAO Cost Estimating and Assessment Guide, GAO-20-195G, March 2020
GAO-20-195G, March 2020; read 2026-08-24.
Cite this page
Projects Advisors, “Earned value calculator,” revised 2026-11-02, https://projects-advisors.com/tools/evm
What the output feeds
- Framework domain 02.3: Forecast credibility
The argument this tool tests
A forecast that never moves is not stable, it is unexamined